EPC project logistics

What does a project logistics manager do?

Gert Geeve, CSCP7 min readUpdated 4 November 2026

A project logistics manager plans and controls the movement of everything an industrial project buys — from the moment it is ordered to the moment it stands on its foundation. On an EPC project that means writing the logistics execution plan, contracting forwarders and carriers, chartering vessels for heavy and out-of-gauge cargo, managing customs, insurance and claims, and keeping procurement and construction aligned.

The role in one sentence

Engineering decides what gets built. Procurement decides where it is bought. The project logistics manager decides how it physically gets there, by when, at what cost and at whose risk — and then makes it happen.

That last part is what separates the job from a planning role. A logistics manager on a project of any size spends as much time on contracts, claims and expediting as on routes and schedules.

Where the role sits

The same shipment is seen differently by each party. A project logistics manager can sit on any of these four seats, and the job changes accordingly.

PartyWhat they carryWhat the logistics manager does there
OwnerSchedule and total project riskSets requirements, audits the EPC contractor’s plan, protects the start-up date
EPC contractorA lump sum, usually fixedEngineers the shipping arrangements and keeps them inside the budget
ForwarderExecutability of the instructionTurns a project schedule into bookings, documents and customs clearance
CarrierVessel space and stabilityMatches cargo to tonnage, stowage and a sailing schedule

What the job covers

On a large EPC project the scope usually runs across all of the following.

  • Logistics execution plan. The document that sets out routes, modes, responsibilities, Incoterms, packing and marking, customs strategy and insurance.
  • Contracting. Tendering and awarding transport, forwarding, export packing, surveys and customs brokerage, then managing those contracts.
  • Chartering. Selecting and booking semi-submersible, heavy-lift or breakbulk tonnage, including part charters, and negotiating the charter party.
  • Customs and compliance. Export and import, temporary admission, origin, sanctions screening and the documents that keep cargo moving.
  • Insurance and claims. Marine cargo cover, deductibles, survey regimes and the claims procedure before anything is damaged.
  • Routing and the last mile. Module yard to marshalling yard to site, including heavy transport over the final kilometres and the laydown area at the other end.
  • Expediting. Chasing packers, carriers, agents and surveyors so that the plan survives contact with reality.

How it differs from a supply chain manager

A supply chain manager optimises a flow that repeats: the same goods, the same lanes, week after week, with total cost over time as the measure. A project logistics manager moves a one-off set of unique items, many of which exist only once, against a construction date that was fixed years earlier.

That changes what counts as a good decision. In a repeating supply chain, saving a few percent per shipment compounds into real money. On a project, a shipment that arrives two weeks late can idle a construction crew of hundreds — so the cheapest routing is frequently the wrong one.

A concrete example

On a four-billion-euro petrochemical project in Antwerp, revising the shipping arrangements that the EPC partners had engineered produced more than €20 million in savings across 14 semi-submersible and 15 heavy-lift sailings. When the Red Sea became impassable and vessels had to route around the Cape of Good Hope, that margin absorbed the extra cost instead of the project budget.

When a project needs one

The honest answer is earlier than most projects arrange it. The decisions that determine transport cost are made during engineering: how equipment is split into transportable pieces, where the fabrication yards are, which port is used and what the module weights become.

By the time purchase orders go out, the transport method is effectively fixed. A logistics manager brought in at that point can still execute well, but the expensive choices have already been made by people who were not thinking about vessel stability or quay strength.

What good looks like

A project where logistics is working well is quiet. Equipment arrives in the order construction needs it, customs holds nothing, surveyors sign off without arguments, and the laydown area does not fill with items nobody can install yet. None of that happens by accident.