Exceptional transport: the exemption and the route survey

Gert Geeve, CSCP8 min readUpdated 27 November 2026

Exceptional transport is any road move that exceeds the legal dimensions or weights: too long, too wide, too high or too heavy. In the Netherlands it needs an exemption from the RDW, the Dutch vehicle authority, and that exemption is not a formality but the outcome of a route that has been demonstrably engineered. Start too late and the exemption sets your schedule, instead of the other way round.

When a transport becomes exceptional

As soon as a combination falls outside the normal limits. Roughly: longer than 22 metres, wider than 3 metres, higher than 4 metres or heavier than 50 tonnes. For project cargo that is the rule rather than the exception — a reactor, a transformer or a module exceeds all four at once.

Worth knowing: the limit decides not only whether you need an exemption, but also which one. The heavier and wider the load, the more the route becomes decisive and the longer the lead time.

Three kinds of exemption

  • Long-term exemption. For a vehicle combination that runs regularly, within fixed dimensions, on a pre-approved road network. Valid for up to five years.
  • Single-trip exemption. For one transport over one route. This is what project cargo usually needs.
  • Bespoke exemption for the heaviest cases, where every structure along the way — bridge, viaduct, culvert — needs its own calculation.

The first two run through the RDW. As soon as provincial or municipal roads are involved, which is almost always, those road authorities join as advisers. Each of them can set conditions, and each of them has its own lead time.

The lead time is the real risk, not the cost

A single-trip exemption for a simple route can be arranged in a few working days. A heavy transport over a route with several structures that need calculating can take six to twelve weeks — and longer if a road authority asks for a load test or a structural review. That time is rarely in the project schedule, because the exemption is seen as something the haulier “just sorts out”. Put the application date in the project schedule, not the transport date.

What belongs in a route survey

The exemption follows from the route, so the route survey is the real work. What it must cover:

  • Clearance height under every viaduct, pipe bridge and overhead line, measured rather than taken from a map.
  • Swept paths at every bend, roundabout and junction, using the actual combination length.
  • Load capacity of structures: bridges, viaducts, culverts and verges, together with the axle load distribution of the combination.
  • Obstacles that have to go: lamp posts, traffic signs, gantries, sometimes a section of crash barrier — including who arranges that and who pays for it.
  • Time windows: many heavy transports may only run at night or outside rush hour, which determines the driving time and therefore the number of nights.

A route survey older than a few months is suspect. Roadworks, a new viaduct or a temporary diversion can make a previously approved route unusable overnight.

SPMT transport: when it is the answer

For the heaviest pieces, SPMT transport comes into view — self-propelled modular transporters, which drive and steer themselves and whose modules can be coupled at will. Axle loads can be kept low by putting more axles under the load, and that is exactly why they are often decisive at bridges and other structures.

They are not meant for long distances on public roads, though. SPMTs move at walking pace and cost a lot per kilometre. The usual picture is therefore combined: by water as close to site as possible, then SPMTs for the last kilometres and the load-out onto the foundation.

Where it goes wrong in practice

  • Exemption applied for too late, because the transport date was in the schedule and the application date was not.
  • Route changed after approval. A different exit is a different exemption.
  • Dimensions taken from the drawing instead of the actual piece. Packing, a transport frame or a protruding flange all count.
  • No attention to the final metres. The road to the site is approved, the site entrance is not.
  • Belgium and Germany treated the same. Different authorities, different limits, different lead times — a Dutch exemption stops at the border.

What this means for your schedule

Treat the exemption as a long-lead item, just like the steel order or the vessel. Decide during design which pieces will become exceptional, have the route surveyed before the dimensions are frozen, and put the application date — with the lead time of the slowest road authority — in the project schedule. Then the exemption no longer decides when your module can move.